§ 20.08.250. Grading report.  


Latest version.
  • When grading involves cuts or fills in excess of fifteen feet in height, or involves fills placed over a swamp, pond, gully or lake, the permittee shall submit an engineer's report upon the completion of such work. This report shall contain:

    A.

    A description of materials used in the fill and its moisture content at the time of compaction, the procedure for deposit and compaction of fill, the preparation of original ground surface before making the fill, and a plan showing the location of compaction tests made in the fill together with a tabulation of relative compaction densities obtained at each location;

    B.

    The recommended soil bearing pressures for proposed structures;

    C.

    A certification by an engineer that the work was done in conformity with the approved plans.

(Ord. 2684 § 21, 1998: Ord. 816 § 1 (part), 1975: prior code § 24-3.1(h))